March 30 - The second floor and roof are framed.

April 1 - Began installation of the furnaces

April 5 - Electrical rough-in

April 6 - Roof shingles

April 7 - Plumbing rough-in

April 9 - Insulated the walls

Foyer
April 12 - Drywalled the garage and most of the ceilings

Owner's Bedroom
April 13 - Drywalled most of the second floor and the laundry room


April 20 - Bricked foundation

 

 